1.9 Stage of Completion Calculation
The contract is the main reference.
Methods may include:
1.
The proportion that
costs incurred for the work to date relate to the estimated total costs.
Example:
You
are building a new computer center, for which your costs will be $10 million. So
far you have spent $4million. Assume that the project is 40% complete, unless
there is any evidence to the contrary.
2.
Surveys of the work
done.
Example:
You
are building a duplicate securities trading center as part of your client’s
disaster plan. . The client’s surveyors have confirmed that 37% of the
work is complete, and recommended payment for the work.
3.
Completion of a
physical portion of the work.
Example:
You
are building 300 branches of similar size. 75 are complete, and no work has
been done on the other 225. Treat your contract as 25% complete, unless there
is any evidence to the contrary.
Costs incurred relating to future work
on the contract, including advance payments to subcontractors, should not be
included in the calculation.
Note: Progress
payments and advances received from clients often do not reflect the
work done.
Example:
On signing a contract to build a
credit card clearing house, you receive a payment of 10% of the contract
price.
Treat this as deferred income (a
liability), and do not recognize any revenue, at this time.
|
When
the outcome of a construction contract can be estimated reliably, contract
revenue and contract costs associated with the construction contract should be
recognised at the balance sheet date.
When
the outcome of a Contract cannot be estimated:
q No profit is recognised, though
an expected loss should be recognised immediately.
q Revenue should only be recognised
to the extent that it is likely to be chargeable to the client.
q Costs should be recognised in the
period in which they are incurred.
Example:
Should
an entity recognise a construction contract work in progress balance at year-end?
Background
E
has recently started to design and construct web sites for its
customers. This is a new activity for
E and it is not clear yet how long such work will typically take; however, it
is clear that the activities will be likely to start in one accounting period
and end in the subsequent one.
Solution
Management
should not recognise construction contract work in progress in respect of the
costs incurred on the web sites. All costs should be expensed as incurred.
Construction
contract accounting also applies to rendering services. However, management
does not have a clear and reasonable estimate of the costs likely to be
incurred in the development of each web site.
The
costs therefore do not meet the recognition criteria for construction contract
work in progress.
Revenue
should be recognised only to the extent that management believes the costs
will be recovered. Management will therefore need to defer all revenue until
the end of the contract if there is uncertainty about collectability.
Management
will be able to recognise work in progress and follow the normal principles
for construction contract revenue recognition once it has established a track
record of web site development costs. This is likely to be after the first
financial year.
|
Common
causes of such uncertainty over the outcome include:
1. Financial difficulties of
contractor or client.
Example:
Your client has not paid you for your work
on the agreed date.
Arguments ensue, but you think that your
client has serious financial problems, and the contract is at risk.
2. Pending litigation or
legislation.
Example:
You are rebuilding on an old industrial site.
The government finds toxic effluent has been leaking from the site, and applies
to the court for an order to stop work.
3. Lack of clarity in the contract
on reimbursement of costs.
Example:
You are building a client service centre.
Government officials demand additional health and safety features, which are
not covered by the contract. You submit a variation proposal to the client, who
refuses it, claiming the cost is yours.
4. Anticipated failure to complete the contract.
Example:
You are building a call centre. Part of the site
unexpectedly becomes flooded, and you cannot determine whether or not the call
centre will be completed within the contract period.
Example:
You are constructing a building for
a client. Project revenue is $20m.
Costs to date are $6m, and you
estimate that additional costs to completion are $10m.
(Costs have been accumulated in an
asset account: construction in
progress. An alternative method is to expense them as incurred.)
The client has, so far, only
approved $4m of the expenditure, as his staff is on holiday for the month.
You believe that the $2m ($6-$4m)
will be approved). No payment has been received.
Recognise:
$4m as expense (the amount approved)
$5m as (accrued) revenue
(4/16*$20m).
$2m is left as construction in
progress. ($6m-$4m=$2m)
I
= Income statement, B = Balance sheet
|
|||
|
I/B
|
DR
|
CR
|
Cost of sales
|
I
|
$4m
|
|
Construction
in progress
|
B
|
|
$4m
|
Accounts receivable
|
B
|
$5m
|
|
Revenue
|
I
|
|
$5m
|
Revenue
recognition
|
|
|
|
Revisions to estimates do not mean
that the financial outcome of the transaction cannot be reliably measured.
Advances and progress payments received from
clients may not reflect the stage of completion.
Example: Percentage of Completion -1
On day 1 of a $50 million contract,
$5 million is received on account.
This should not be fully recognised
as revenue until 10% of the work has been successfully completed.
|
|||
|
I/B
|
DR
|
CR
|
Cash
|
B
|
$5m
|
|
Deferred
revenue
|
B
|
|
$5m
|
Recording
cash receipt on day 1
|
|
|
|
Example: Percentage of Completion -2
10% is now
completed, costs total $3m
|
|||
Cost of sales
|
I
|
$3m
|
|
Work in
progress
|
B
|
|
$3m
|
Deferred revenue
|
B
|
$5m
|
|
Revenue
|
I
|
|
$5m
|
Revenue
recognition –when 10% of the work is completed
|
|
|
|
In the early stages of a transaction,
it may be that the profitability cannot be reliably estimated.
If it is likely that only the costs
will be recovered, recognise only enough revenue to equal the costs. (accounting
for the project as breakeven: no profit, no loss).
Example: Recovery of costs
Project revenue is a total of $100
million. $1 million has been spent at the period end, and there are problems
that indicate that no profit will be made on the project.
Recognise $1million as accrued
revenue and $1million as (actual) expenses.
|
|||
|
I/B
|
DR
|
CR
|
Accounts
receivable
|
B
|
$1m
|
|
Revenue
|
I
|
|
$1m
|
Revenue
recognition
|
|
|
|
Cost of sales
|
I
|
$1m
|
|
Work in
progress
|
B
|
|
$1m
|
Recognising
expenses
|
|
|
|
If it is not probable that the costs will be
recovered, no revenue is recognised, and all costs are immediately expensed.
Property type- different accounting treatment applied to properties under IFRS
depending on their current and future uses and their ownership
|
Standard Number
|
Standard Name
|
Valuation
|
Owner-occupied
property
|
IAS 16
|
Property,
plant and equipment
(see
also IAS 20 Government grants)
|
Cost
or revaluation.
|
Property
under construction (including investment property under construction)
|
IAS 16
|
Property,
plant and equipment
(see
also IAS 23 Borrowing costs)
|
Cost.
|
Property
acquired in an exchange of assets
|
IAS 16
|
Property,
plant and equipment
|
Fair
value or the carrying amount of the assets given up.
|
Investment
property
|
IAS 40
|
Investment
property
|
Cost
or fair value.
|
Investment
property being redeveloped for continuing use as investment property.
|
IAS 40
|
Investment
property
|
Cost
or fair value.
|
Investment
property held for sale without development (unless it meets the criteria of
IFRS 5 – see below).
|
IAS 40
|
Investment
property
|
Cost
or fair value.
|
Property
held under an operating lease classified as an investment property
|
IAS 40
|
Investment
property
|
Fair
value (accounted for as a finance lease under IAS 17).
|
Property
held under a finance lease
|
IAS 17
|
Leases.
Owner-occupied IAS 16,
Investment property IAS 40.
|
The
lower of fair value and the present value of the minimum lease payments.
|
Property
held under an operating lease – owner -occupied
|
IAS 17
|
Leases
|
Leasing
costs expensed.
|
Property
lease to another party under a finance lease
|
IAS 17
|
Leases
|
Account
receivable equal to the net investment in the lease.
|
Property
sale and leaseback
|
IAS 17
|
Leases
|
As
operating lease or finance lease, as appropriate
|
Trading
properties – property (including investment property) intended for sale in
the normal course of business or being built or developed for that purpose
|
IAS 2
|
Inventories (Properties held for sale that meet the
criteria of IFRS 5 should be recorded according to IFRS 5 – see below. These
are generally not in the normal course of business.)
|
Lower
of cost and net realisable value.
|
Property
held for sale, or included in a disposal group that is held for sale.
|
IFRS 5
|
Non-current
assets held for sale and discontinued operations
|
Lower
of carrying amount and fair value less costs to sell.
|
Assets
received in exchange for loans (taking possession of collateral)
|
IFRS 5
IAS 16
|
Non-current
assets held for sale and discontinued operations
Property,
plant and equipment (see Property acquired in an exchange of assets above)
|
Lower
of fair value less costs to sell and carrying amount of the loan net of
impairment at the date of exchange.
(see
HSBC plc Annual Report 2005 page 247)
|
Property provided
as part of a construction contract
|
IAS 11
|
Construction
contracts
|
Stage of contract
completion or cost.
|
Future
costs of dismantling, removal and site restoration.
|
IAS 37
|
Provisions,
contingent liabilities and contingent assets (see also IFRIC 1, IFRIC 5)
|
Present
value of the expected costs, using a pre-tax discount rate.
|
Notes to the table
on the previous page.
Note 1:
Where an asset is revalued,
increases in carrying amounts above cost are recorded as revaluation surplus, in
equity.
Using fair values, all changes in fair value are recorded in the income statement.
Reductions below
cost are recorded in the income statement under both methods.
Note 2.
In the cases of cost or revaluations, the carrying value will be reduced by
accumulated depreciation and accumulated impairment (see IAS 36).
Workbooks are available on our website on each
standard that explain each accounting treatment with examples.
|
No comments:
Post a Comment