IAS 11: Contract Revenue

1.6 Contract Revenue


Contract revenue should comprise:

1.     The initial revenue agreed; and

2.     Variations in the contract work, claims and incentive payments.
(These are included if it is probable that they will result in revenue, and are capable of being reliably measured).

The contract revenue may change from one period to the next, as a result of contract variations, claims, penalties, and cost-escalation clauses.
Variations may increase, decrease, or redesign the scope of the contract, with a matching change in revenue.

Changes are only included in revenue when it is likely that the client will approve the variation and its impact on the revenue, and the change in revenue can be reliably measured.

Example:
You are building a road. The original plan called for a bridge over a railway, but the authorities now insist on a tunnel under the railway instead.

This is a variation.

Claims are levied by the contractor on the client for costs not included in the contract price. Often, these stem from problems caused by the client, such as wrong specifications, errors in designs, and delays.

Example:
You have been contracted to demolish some houses, and build a clearing house. You were promised vacant possession. When your staff arrives, they find that the tenants still occupy the old houses. It takes a month to re-house them, delaying the start of work.

This may be the basis for a claim.

Clients may contest the claims, so they should only be included in project revenue when the amount of the claim that is likely to be paid can be reliably determined.

Incentive payments are bonuses paid if the contractor meets or exceeds specific criteria, such as early completion of part, or all, of the contract. They are included in contract revenue when it is likely that they will be earned.

Example:
You are building a head office. If the actual completion date is a month (or more). earlier than the planned completion date, your firm will earn a bonus (and the client can start operations early)..

This is an example of an incentive payment.

Contract estimates need to be revised, either for actual performance, or new considerations of future performance.

Example:
You are redeveloping a retail site in the city centre. You had planned to work 24 hours per day, but the city has just passed regulations to halt building work at night.

You may have to revise your contract estimate.


Example:

Progress payments and advances received from clients often do not reflect the work performed. On what basis should management assess a project’s percentage of completion?

Background
P entered into a contract with B to construct a clearing centre. The cost of the clearing centre is estimated at 150,000. The total revenue from the contract is estimated at 200,000. P will take 3 years to construct the clearing centre.

At the end of year 1 P incurred costs of 60,000. The client was invoiced for 50,000 at the end of year 1. Payment of this progress billing is due, early in year 2, in accordance with the normal credit terms that P offers. 

Management estimated the stage of completion as 33%, based on the amount invoiced.

Solution
The percentage of completion should be determined from: the proportion of costs incurred to date; the percentage of physical work complete; or services performed to date. Amounts invoiced to clients do not necessarily influence the stage of completion.

Based on the relationship between the costs incurred to date and total estimated costs, the contract is 40% (60,000/150,000) completed at the end of year 1. Revenue of 80,000 (40% of 200,000) should be recognised at the end of year 1.

The 50,000 progress billing invoiced to the client should be recognised as an adjustment to construction account receivable in the balance sheet. The construction account receivable balance is disclosed separately on the face of the balance sheet.

No comments:

Post a Comment